
Procedure for obtaining demolition notification in municipality - step-by-step guide
Detailed guide to demolition notification procedure in municipality. Learn when notification suffices instead of permit, what documents to prepare and how to avoid refusal.
Procedure for obtaining demolition notification in municipality - step-by-step guide
Introduction
Demolition notification is a simplified administrative procedure that in certain cases replaces demolition permit. According to Art. 29 sec. 1 point 20 of the Construction Law Act, notification can be submitted for objects of limited volume and area. This procedure saves time and costs but requires meeting strict criteria.
When is notification sufficient instead of permit?
✅ Objects qualifying for notification
Single-family residential buildings:
- Built-up area up to 35 m²
- Height up to 8.5 m (to highest roof point)
- Maximum 2 above-ground floors
Utility buildings and garages:
- Built-up area up to 35 m²
- Height up to 5 m
- No underground floors
Structures and temporary objects:
- Garden sheds up to 25 m²
- Shelters and canopies up to 50 m²
- Fences up to 220 cm height
❌ Objects requiring permit
Absolute exceptions:
- Heritage-listed objects
- Buildings in conservation protection zone "A"
- Objects in flood-risk areas
- Buildings containing asbestos (require special procedure)
Step-by-step procedure
STEP 1: Documentation preparation (Time: 7-14 days)
Mandatory documents:
Demolition notification form
- Available on municipality website
- Completed legibly and signed
- Can be submitted electronically via ePUAP
Object situation sketch
- Drawn to scale (recommended 1:500)
- Showing location on plot
- With dimensions and distances from boundaries
Property right confirmation documents
- Current land register extract
- Loan/lease agreement (if applicable)
- Power of attorney (for representatives)
Photographic documentation
- Object photos from different sides
- Technical condition of structure
- Surroundings and neighborhood
STEP 2: Local plan compliance verification (Time: 1-2 days)
Municipality office verification:
- Checking development plan provisions
- Confirming no additional restrictions
- Determining any special requirements
Possible limitations:
- Landscape protection
- Sanitary zones
- Public purpose investment areas
STEP 3: Utility network agreements (Time: 7-21 days)
Mandatory agreements:
Electricity:
- Notification to energy company
- Implementation deadline: 7-14 days
- Cost: usually free
Natural gas:
- Disconnection application to gas company
- Site inspection required
- Cost: 150-400 PLN
Water and sewerage:
- Notification to water company
- Water meter removal
- Cost: 80-250 PLN
Telecommunications:
- Operator notification
- Installation removal at owner's cost
- Timeline: 3-7 days
STEP 4: Notification submission (Time: 1 day)
Where to submit:
- Municipality/city hall - architecture department
- Electronically via ePUAP
- In person during office hours
Required fees (as of 2025):
- Notification fee: 92 PLN
- Stamp duty: 17 PLN
- Total fee: 109 PLN
Payment methods:
- Cash at office cashier
- Bank transfer to office account
- Online payment (ePUAP system)
STEP 5: Waiting period (30 days)
Office activities:
- Formal document completeness check
- Substantive regulatory compliance assessment
- Possible supplementation requests
- Development plan compliance verification
Possible office decisions:
1. No objection (administrative silence)
- Work can begin after 30 days
- No additional formalities
- Most common situation (approx. 85% of cases)
2. Objection filing
- Office issues objection decision
- Demolition permit required
- Appeal possible to self-government appeals board
3. Supplementation request
- Term is interrupted
- 7 days for document supplementation
- New 30-day term from supplementation
STEP 6: Work commencement (after 30 days)
Pre-commencement obligations:
- Neighbor notification (recommended in writing)
- Construction site securing
- Responsible person designation
Implementation requirements:
- Working hours compliance (usually 7:00-18:00)
- Minimizing neighborhood nuisance
- Proper waste disposal
Most common reasons for office objection
1. Formal problems (40% of cases)
Incomplete documentation:
- Missing situation sketch
- Incorrect object dimensions
- Outdated ownership documents
Form errors:
- Incorrect plot data
- Missing owner signature
- Inconsistency with land register data
2. Parameter exceedance (35% of cases)
Object dimensions:
- Area exceeding 35 m²
- Height exceeding limits
- Additional floors
Location:
- Too close to plot boundary
- In protected area
- In height restriction zone
3. Special requirements (25% of cases)
Environmental protection:
- Suspected asbestos presence
- Threat to protected species
- Groundwater impact
Safety:
- Threat to adjacent objects
- Unresolved technical issues
- Lack of network manager agreements
Total procedure costs
Office fees: 109 PLN Technical documentation: 300-800 PLN Network agreements: 200-650 PLN Geodetic documents: 200-500 PLN Total: 809-2059 PLN
Comparison with demolition permit:
- Time savings: 35 days
- Cost savings: 2000-4000 PLN
- Less complicated procedure
Implementation timeline in 2025
Document preparation: 7-14 days Network agreements: 7-21 days Notification submission: 1 day Decision waiting: 30 days Total time: 45-66 days
Practical advice
✅ How to increase acceptance chances
1. Thorough preparation:
- Checking all object dimensions
- Current ownership documentation
- Clear and accurate sketch
2. Early consultations:
- Discussion with officer before submission
- Local requirements verification
- Surveyor consultation
3. Document completeness:
- All required attachments
- Proper form completion
- Current agreements
❌ Errors to avoid
1. Imprecise measurements:
- Incorrect area determination
- Improper height measurement
- Missing structural elements
2. Late agreements:
- Last-minute network contact
- No time for possible corrections
- Not considering technical deadlines
3. Procedure negligence:
- Starting work before 30 days
- No neighbor notification
- Non-compliance with notification conditions
Appeals and legal remedies
In case of office objection:
1. Appeal to SOK (Self-government Appeals Board)
- Deadline: 14 days from decision delivery
- Fee: 183 PLN
- Processing time: up to 60 days
2. Administrative court complaint
- After exhausting appeal process
- Deadline: 30 days from SOK decision delivery
- Fee: 200 PLN
3. Alternative solutions
- Re-notification after removing objection causes
- Demolition permit application
- Demolition project modification
Controls and violation consequences
Types of controls:
- Formal document control
- Site inspection before commencement
- Controls during work execution
Violation penalties:
- Starting work before deadline: 500-5000 PLN
- Exceeding declared parameters: 1000-10000 PLN
- Lack of network agreements: 2000-20000 PLN
Bibliography
Legal acts:
- Construction Law Act of July 7, 1994 (consolidated text: Journal of Laws of 2024, item 725, Art. 29 sec. 1 point 20)
- Regulation of the Minister of Infrastructure of June 26, 2002 on construction diary (consolidated text: Journal of Laws of 2024, item 1120)
- Administrative Procedure Code Act of June 14, 1960 (consolidated text: Journal of Laws of 2024, item 572)
Official sources:
- Ministry of Development and Technology - Construction Procedures Guide 2025
- Portal gov.pl - Building demolition notification, access: 2025
- Association of Polish Cities - Administrative Procedure Standards in Construction, 2025
- General Office of Building Control - Construction Law Interpretations, 2025
Tags
Share this guide
About the author
Piotr Nowak
Administrative Procedures Specialist at Tree Group
Category
Legal Aspects
Reading time
10 minutes
Publication date
May 30, 2025
Similar guides

Legal Aspects of Demolition and Earthworks - Comprehensive Guide
A comprehensive guide to legal requirements related to demolition and earthworks. Learn what permits are necessary, how ...

Permission for demolition in Warsaw - complete guide 2025
Complete guide to obtaining demolition permits in Warsaw. Learn what documents are needed, permit costs, and how to avoi...